We are sorry for inconveniences that community center users have experienced but believe that once the work is completed we will have a much better center --that will be more comfortable, more energy efficient, a more reliable pool, etc.. Thanks for your interest!
PAUL FEINER
The
Department of Public Works is working on several projects at the Community
Center to improve the pool and gym. At this time a project is being bid to
replace the ventilation system at the indoor pool and to replace the heating and
air-conditioning system in the gym. The pool ventilation system has been poorly
performing for some time. Fans are often placed around the pool deck to help
provide ventilation as the existing system is not able to provide a level of
comfort expected. The Town is bidding a project that will replace and redesign
the mechanical ventilation systems for the pool.
In
addition to the replacement of the ventilation system, the Town secured a grant
from the U.S. Department of Energy in the amount of $169,000 to install a Solar
Hot Water Heating System for the swimming pool. This project is construction
included with the ventilation and air-conditioning project that is now out to
bid. It is expected the Solar Hot Water Heating System will reduce the energy
costs to heat the pool. Coupled with new work on the pool mechanicals, we
expect the comfort of the pool and reliability of the pool heating systems to be
greatly improved with both the solar hot water heating and new ventilation
system.
Also
now bidding with the pool project is a new heating and air-conditioning system
for the Gym. Historically, the gym systems have been unreliable, poorly
functioning and susceptible to leaking water onto the gym wood floor. They are
noisy, disruptive and do not provide adequate cooling or heating of the gym at
times. The Town plans to replace the existing units with new more efficient
units. The new units will no longer be hanging from the gym ceiling, but will
instead be installed above, outside on the gym roof. The new units are expected
to provide much better temperature control to the gym and, as they are no longer
in the gym, the amount of noise from the fans will no longer be a problem during
events.
In
the next week, bids will be received for these projects. A recommendation for
project award is expected to the Town Board before the end of October. With no
complications, we are expecting work to commence before the end of 2012 on the
Solar Hot Water heating and ventilation system for the pool as well as new
air-conditioning and heating for the gym.
Since
last August, the gym has been closed from the flooding after Hurricane Irene.
Flooding from the Manhattan Brook caused the old wood floor to buckle. The
extent of the buckling of the old wood floor was compared to a skate park by
some. The repair to this floor has taken considerable time. Asbestos was found
contained in the glue that originally held the wood floor strips onto the
existing concrete floor. This material required special handling to remove
properly and not create any health hazard within the Community Center. The
flooring, glue and all traces of asbestos containing material is now all removed
from the gym. Recently, the Town Board directed that a new wood floor be
installed as a proper surface for the Community Center gymnasium needs. The
Town is nearing completion on the details and specifications for a new and
improved wood floor. It is expected bidding will occur during October for the
installation of the new wood gymnasium floor. If the project stays on schedule,
the flooring installation should be underway during the winter months with an
expectation to have the gymnasium flooring ready by the early Spring of
2013.
To
help reduce the chances of future flooding damaging the TDYCC, the Town has
applied for grant funding to implement a “ flood-proofing” project for the
Community Center. Installation of a series of automatically operating flood
gates successfully blocked stormwater from entering a hospital in upstate New
York in a flood event. A consultant working for the Town suggested a similar
system could possibly be employed to block flood waters from entering the TDYCC
through the doorways. It was our experience during Hurricane Irene that the
flooding of the gym and other areas of the Community Center occurred as water
entered through the doors along the side and back of the building. By
installing movable flood gates, it is hoped that future flood water will be
blocked from these entrance ways. We have proposed this solution to FEMA and
are now awaiting word on a possible grant award to fund this
endeavor.
A
final project nearing design completion is the replacement of the roof for the
Lois Bronz Children’s Center. This project should be ready for bid also during
October. Actual replacement of the roof may not occur until spring or maybe
even summer of 2013 as roofing projects are very dependent upon the weather and
temperature for construction.
In
the coming year, the Department of Public Works hopes to continue to improve the
Community Center as well as the Louis Broz Children’s Center so these facilities
can continue to provide to the community for many more years.
0 comments:
Post a Comment