The indoor pool at the Theodore Young Community Center
is over 30 years old. The main pump is not working. Once the pump is rebuilt,
the pool can be refilled and the water can be heated up so that it can be used.
Commissioner of Public Works Victor Carosi advised me tonight that the main pump
has been removed and is being serviced. Contractor advises parts are scheduled
to arrive Friday. Contractor will work Saturday to rebuild the pump.
Re-installation scheduled for Monday, Feb 11. If all stays on schedule, pool
should be ready to open Thursday.
Unknown that may affect schedule is forecast for snow Friday
if it impacts delivery of parts and ability of contractor to work. We apologize
for the inconvenience and promise you that we're doing what we can to expedite
the pool repairs.